Brownfield ISD

New High School Campus

Size: 148,000 SF

Delivery Method:
Construction Management at Risk

Original GMP: $32.7M

Final GMP: $32.5M

Completion: August 2022

This comprehensive high school campus includes a sunken competition gym with a basement housing multiple locker rooms, a separate practice gym, a cafetorium, CTE woodshop, metalworking and automotive wings, administrative offices, and classrooms. Polished concrete finishes in hallways and common areas create a modern, durable environment. Despite material delays due to COVID-19 and owner-directed changes (including new land acquisition and additional access), Sandia delivered a facility tailored to Brownfield ISD’s evolving needs.

Key Services:
  • Budgeting & cost estimating
  • Scheduling & subcontractor coordination
  • Self-performed building concrete, rough carpentry, doors/hardware, and specialty installations.